THE Department of Public Works and Highways (DPWH) is expecting to complete the P3.13-billion Bucana Bridge in Davao ahead of its target completion timeline after the project entered its final phase.
The 1.34-kilometer Davao River (Bucana bridge) is now 85% complete, the DPWH said.
The project’s final bridge deck connection is projected to be finished by June which would give way for final works, allowing the bridge to be operational by November.
The project, consisting of a four lane, six-span bridge, is set to enhance mobility and connectivity in Davao City, the agency said.
DPWH Senior Undersecretary Emil K. Sadain said the Bucana bridge project is also anticipated to improve traffic congestion in Davao City by accommodating up to 35,000 vehicles per day.
The DPWH said the Bucan bridge project is also projected to bring economic opportunities by connecting Davao’s east and coast areas and enhancing access to essential services while also promoting agricultural and commercial activities in the region.
The project, targeted to be completed by the third quarter, is funded through an official development assistance grant from China.
The Bucana bridge also features a 480.20-meter extradosed design, with each pier supported by 10 stay cables, described as an innovative engineering solution. — Ashley Erika O. Jose