Farm-to-road projects delayed by high fuel costs

3 weeks ago 16
Suniway Group of Companies Inc.

Upgrade to High-Speed Internet for only ₱1499/month!

Enjoy up to 100 Mbps fiber broadband, perfect for browsing, streaming, and gaming.

Visit Suniway.ph to learn

MANILA, Philippines — Rising fuel costs amid the Middle East conflict forced the Department of Agriculture (DA) to delay by about one month the implementation of nationwide farm-to-market road (FMR) projects. The agency originally targeted to begin construction of FMR projects in April. It received a budget allocation of P33 billion under the 2026 General